[单选题] A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear o

A、4 weeks

B、5 weeks

C、6 weeks

D、7 weeks

参考答案:

B、5 weeks