问题:
A、assign change tasks to project members
B、call a meeting of the configuration control board
C、change the scope baseline
D、postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline
D、postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline
● 参考解析