[单选题] A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a

A、Tell the customer that he will not address any problems

B、Tell the customer that the problem is not sufficiently defined to company to a solution

C、Collect as much information on the problem without committing his company to a solution

D、Give the customer a range of solutions that might be acceptable to his company

参考答案:

C、Collect as much information on the problem without committing his company to a solution