问题:

[单选题] Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.

A、work breakdown structure

B、baseline

C、software requirements specification

D、plan

参考答案:

A、work breakdown structure

  参考解析