当前位置: 首页 > IT认证 > 软件水平

问题:

[单选题] Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends up

A、Finish-to-Start

B、Finish-to-Finish

C、Start-to-Start

D、Start-to-Finish

参考答案:

A、Finish-to-Start

  参考解析

试题来源参考:

公众号搜题更便捷

    扫码关注题大师公众号

    文字、语音、截图都可搜题

    亿级题库 秒出结果

相关题库