问题:

[单选题] The intention of the ( ) is to schedule,organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.

A、project work breakdown

B、project security authentication

C、project management

D、project flowchart

参考答案:

C、project management