[单选题] The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , th

A、Measure, delay, record, distribute, analyze, and direct

B、Plan, schedule, monitor, control, report, and forecast

C、Promote, highlight, monitor, control, forecast, and report

D、Emphasize, visualize, analyze, conceptualize, report and record

参考答案:

B、Plan, schedule, monitor, control, report, and forecast